Current report no 40 / 2022

Current report no 40 / 2022 - 5 July 2022 / 16:37

Design and construction of the S17 Piaski - Hrebenne express road, section 9 Tomaszów Lubelski (end of the ring road) - Hrebenne (start of the ring road), with a length of approx. 17.3 km - the bid of Budimex S.A. evaluated the highest

The Management Board of Budimex S.A. announces that on 5 July 2022, the General Directorate for National Roads and Motorways, Branch in Lublin informed the Company that its bid had received the highest score in the tender procedure for: “Design and construction of the S17 Piaski – Hrebenne express road, section 9 Tomaszów Lubelski (end of the ring road) – Hrebenne (start of the ring road), with a length of approx. 17.3 km“.

This information does not mean selecting the bid of Budimex S.A. as the most advantageous one, as the procedure concerning the bid evaluation has not yet been finally completed.

Bid value: PLN 486,397,390.00 net

Works commencement date: from the date of signing the contract

Works completion date: 36 months from the Commencement Date

Guarantee period for the main works: 10 years

Warranty period: 60 months from the date indicated in the Work Acceptance Certificate

Advance payment: maximum 10% of the Accepted Gross Contract Amount

Payment terms: 30 days from the day of delivery of a correctly issued VAT invoice to the Ordering Party by the Contractor

Bank performance bond: 10% of the Accepted Gross Contract Amount

Maximum amount of contractual penalty paid by the Contractor: 20% of the Accepted Gross Contract Amount

The Ordering Party may seek compensation under general rules if the amount of damage exceeds the amount of the stipulated penalty.

Other terms and conditions of the contract do not differ from the market standards.

The bid value exceeds the threshold of PLN 158,224 thousand net.