Current report no 11/2024

Current report no 11/2024 - 19 February 2024 / 12:04

‎“Construction of the road S10 Szczecin – Piła at the section from the end of Stargard ring ‎road to the beginning of Piła ring road (with “Koszyce” junction), excluding Wałcz ring road, ‎Section 2: “Stargard Wschód” junction /without the junction/ – “Suchań” junction /without ‎the junction/” – the bid of Budimex S.A. rated highest

The Management Board of Budimex S.A. announces that on 19 February 2024, the General ‎Directorate for National Roads and Motorways, Branch in Szczecin, informed the Company ‎that its bid had been awarded the highest score in the tender procedure for: “Construction of ‎the road S10 Szczecin – Piła at the section from the end of Stargard ring road to the ‎beginning of Piła ring road (with “Koszyce” junction), excluding Wałcz ring road, Section 2: ‎‎“Stargard Wschód” junction /without the junction/ – “Suchań” junction /without the ‎junction/”.‎
‎ ‎
The aforementioned information does not mean selecting the bid of Budimex S.A. as the ‎most advantageous one, because the procedure concerning the bid evaluation has not yet ‎been finally completed. ‎

Bid value: PLN 366,166,760.93 net ‎
‎ ‎
Works commencement date: from the date of contract conclusion by both parties

Works completion date: 39 months from the date of contract execution (the implementation ‎time does not include winter periods)‎

Guarantee period for the main works: 15 years

Warranty period: 60 months from the date indicated in the Work Acceptance Certificate

Advance payment: from 1% to 10% of the Accepted Gross Contract Amount

Payment terms: within 30 days of the date of delivery of VAT invoices to the Ordering Party, ‎issued for the amounts certified in Payment Certificates ‎

Bank performance bond: 10% of the Accepted Gross Contract Amount

Maximum amount of contractual penalty paid by the Contractor: 20% of the Accepted Net ‎Contract Amount

The Ordering Party reserves the right to demand supplemental damages in excess of ‎contractual penalties up to the amount of actual loss that was incurred or could be incurred ‎due to the non-performance or improper performance of the contract by the Contractor. ‎

Other terms and conditions of the contract do not differ from the market standards.‎

The bid value exceeds the threshold of PLN 172,381 thousand net.‎