Current report no. 36/2024

Current report no. 36/2024 - 10 April 2024 / 10:35

Design and execution of construction works for the construction of new substations on the railway ‎line No 38 section Ełk – Korsze under the project entitled “Works on the railway line No 38 ‎section Giżycko – Korsze, along with electrification” – signing of the contract

The Management Board of Budimex S.A. announces that on 10 April 2024, the Ordering Party, i.e. ‎PKP Polskie Linie Kolejowe S.A., signed with the Contractor, i.e. a Consortium of companies ‎composed of: Budimex S.A. (Consortium Leader) and Victor Energy Sp. z o.o. (Consortium Partner), ‎an Agreement for the performance of the contract for: Design and execution of construction works ‎for the construction of new substations on the railway line No 38 section Ełk – Korsze under the ‎project entitled “Works on the railway line No 38 section Giżycko – Korsze, along with electrification”.‎
‎ ‎
The information that the Consortium’s bid had been rated the highest in the tender procedure was ‎published on 28.08.2023 in current report No 53/2023.‎
‎ ‎
The information that the Consortium’s bid had been selected as the most advantageous one in the ‎tender procedure was published on 17.01.2024 in current report No 3/2024.‎
‎ ‎
Value of the bid submitted by the Consortium: PLN 233,101,626.02 net, including:‎
a) Basic scope: PLN 195,601,626.02 net
‎• Budimex S.A.: PLN 161,931,673.55 net (Consortium Leader) ‎
‎• Victor Energy Sp. z o.o.: PLN 33,669,952.47 net (Consortium Partner) ‎
b) Contingency: PLN 37,500,000.00 net ‎
‎ ‎
Contract commencement date: the date of conclusion of contract by the Parties ‎
‎ ‎
Contract completion date: 32 months from the date of the contract conclusion
‎ ‎
Guarantee period: 60 months, starting from the Final Acceptance date
‎ ‎
Warranty period: 60 months, starting from the Final Acceptance date
‎ ‎
Advance payment: none
‎ ‎
Payment terms: The Contractor’s remuneration shall be paid within 30 days from the date of the ‎Ordering Party’s receipt of a correctly issued invoice together with the required documents. ‎
‎ ‎
Bank performance bond: 5% of the gross total price for the basic scope specified in the bid less the ‎gross Contingent Remuneration
‎ ‎
Maximum amount of contractual penalty paid by the Contractor: 20% of the net value of the Works ‎or 30% of the net value of the Works (where a penalty for withdrawal from the contract has been ‎charged)‎
‎ ‎
Payment of a contractual penalty does not prejudice the Ordering Party’s right to seek damages ‎exceeding the contractual penalty provided for in the contract, in accordance with general principles, ‎including those resulting from the loss of EU funding, if the loss of this funding was for reasons ‎attributable to the Contractor.‎
‎ ‎
Other terms and conditions of the contract do not differ from the market standards.‎
‎ ‎
The value of the contract exceeds the threshold of PLN 196,030 thousand net.‎