Current report no 9/2024

Current report no 9/2024 - 14 February 2024 / 16:29

‎“Extension and modernisation of the Piła Krzewina station along with switching over the 400 kV ‎line Piła Krzewina – Plewiska operating at a voltage of 220 kV to a voltage of 400 kV” – procedure ‎No 2023/WNP-0223 – Budimex S.A. bid selected

The Management Board of Budimex S.A. announces that on 14 February 2024, Polskie Sieci ‎Elektroenergetyczne S.A. selected the bid of Budimex S.A. as the most advantageous one in the ‎tender procedure entitled: “Extension and modernisation of the Piła Krzewina station along with ‎switching over the 400 kV line Piła Krzewina – Plewiska operating at a voltage of 220 kV to a ‎voltage of 400 kV” – procedure No 2023/WNP-0223.‎

Bid value: PLN 188,722,000 net

Works commencement date: from the Contract date

Works completion date: 45 months from the Contract date (47 months if the Ordering Party ‎exercises Option Right 1)‎

Guarantee period: 5 years

Warranty period: 5 years

Advance payment: 10%‎

Payment terms: 21 days from the day of delivery of a correctly issued VAT invoice to the Ordering ‎Party by the Contractor

Bank performance bond: 5% of Remuneration including VAT ‎

Maximum amount of contractual penalty paid by the Contractor: 20% of Remuneration

The Ordering Party reserves the right to seek damages under generally applicable rules if the ‎amount of loss sustained exceeds the amount of the stipulated contractual penalty up to 100% of ‎Remuneration.‎

Other terms and conditions of the Contract do not differ from the market standards.‎

The bid value exceeds the threshold of PLN 172,381 thousand net.‎